Sahwa@reddthat.com to Fuck AI@lemmy.world · 2 days agoAlmost Half of US Data Centers That Were Supposed to Open This Year Slated to Be Canceled or Delayedfuturism.comexternal-linkmessage-square113fedilinkarrow-up1776arrow-down13
arrow-up1773arrow-down1external-linkAlmost Half of US Data Centers That Were Supposed to Open This Year Slated to Be Canceled or Delayedfuturism.comSahwa@reddthat.com to Fuck AI@lemmy.world · 2 days agomessage-square113fedilink
minus-squareRiskable@programming.devlinkfedilinkEnglisharrow-up47·2 days agoThe reason why is simple: The projects were planned at a high level, the engineers checked all the boxes, and the executives pat themselves on the back. Then they went to order everything and got, “out of stock.”
minus-square✺roguetrick✺@lemmy.worldlinkfedilinkarrow-up26·2 days agoPer the article it’s “Batteries, electrical transformers, and circuit breakers” no less.
minus-squareSteve@startrek.websitelinkfedilinkarrow-up13·2 days agoCircuit breakers are for pessimists
minus-squarevaultdweller013@sh.itjust.workslinkfedilinkarrow-up3·1 day agoLive long or burn down as my uncle Ricky once said. Shame about the fire. This is a joke, I do not have an uncle Ricky as far as I understand.
The reason why is simple: The projects were planned at a high level, the engineers checked all the boxes, and the executives pat themselves on the back.
Then they went to order everything and got, “out of stock.”
Per the article it’s “Batteries, electrical transformers, and circuit breakers” no less.
Circuit breakers are for pessimists
Live long or burn down as my uncle Ricky once said. Shame about the fire.
This is a joke, I do not have an uncle Ricky as far as I understand.